  1. Construction

    1. Hamar House Demolition

      Demolition of the Hamar House begins in early June.

      Following demolition, site work will begin to expand Parking Lot 14, adding 53 new parking spaces for faculty and staff. Lot 14 expansion is expected to be completed in August.

      Lot 14 will temporarily close and Transportation Services will notify permit holders with detailed parking instructions. During construction, nearby academic buildings may experience unavoidable noise and vibrations from heavy equipment and demolition activities. Traffic flow around the area will also be temporarily affected.

      Pedestrian access outside the immediate parking lot area is expected to remain largely unaffected. However, pedestrians are encouraged to please remain alert when traveling through or near construction zones, to respect barricades, and to follow all posted safety instructions on signage.