Please be advised of the following activity that will commence on
Thursday, October 6, 2022
The sequence of work is as follows:
- October 6 – demolish traffic islands in Parking Lot E (two days)
- October 11 – tree removals in Parking Lot E (two days)
- October 17 – demolish and install new concrete in Parking Lots E and F (10 days)
For more information, please reach out to
PETER ESPINOSA, CCM
Sr. Construction Manager
Construction Management Division
505 14TH Street; Suite 1060 | Oakland, CA 94612-1406
office: (510) 763-1313 | mobile: (510) 301-3416
Email: peter.espinosa@stvinc.com
The
Pathways & Parking Lot Improvements project is commencing on Thursday, October 6, 2022 and will be in progress through the beginning of November, 2022..