Construction
Bldg. 410
Student Center
July 30 - November 11, 2026
As part of ongoing campus facility improvements, brick veneer replacement work will begin at Building 410 (Student Center). The project will be completed in phases, with protective fencing installed around each active work area to maintain a safe environment.
Project Schedule
-
Site setup will begin Thursday, July 30.
-
Demolition will begin Wednesday, August 5, at the west stair area and proceed east.
-
Demolition is expected to be completed during the week of August 24.
-
Installation of the new brick veneer will begin Wednesday, August 12.
-
Final completion and cleanup are anticipated by Wednesday, November 11.
Access and Impacts
No major impacts to scheduled Student Center activities are anticipated at this time. Pedestrian and operational access to the building will be maintained throughout the project. Please use caution near designated work areas and observe all posted signage and protective barriers.
We appreciate your patience and cooperation as we complete these facility improvements.
If you have any questions or concerns, please contact John Gaston, Senior Project Manager, Design and Construction, at jgaston1@mtsac.edu.